PLANNING
|
||
GREEN IS
DONE |
YELLOW
IN PROGRESS |
Red- possibly Delay |
Activity |
Completion date |
Responsibilities |
Draft protocol for the
experiment |
May |
Coordinating Group |
Get firm commitments from
participants. |
September |
Coordinating Group and
participants. |
Determine degree of
replication * |
July |
Coordinating Group |
Confirm participants and
locations |
July September |
Paticipants / Coordinating
Group |
Draft Guidelines SEDIMENT |
End of July Septemeber |
Coordinating Group |
Purchase sampler sheets |
June–August |
RIKZ |
Prepare and spike sampler
sheets |
August–September |
RIKZ |
Purchase of bottles |
June–August |
RIKZ |
Prepare, spike bottles |
August–September |
RIKZ |
Distribute bottles |
|
RIKZ |
Build frames to support
samplers |
July–Mid septemberr |
RIKZ |
Purchase
mussels or use local animals |
October |
Participants |
Distribute sample frames |
|
RIKZ |
Distribute sampler sheets |
|
RIKZ |
Deploy mussels and
samplers and sediment |
Early October. |
Participants |
Record supporting data
(CTD-data) |
Simultaneous with the
sampling |
Participants |
Recover mussels and
samplers |
Late November/early
december |
Participants |
Shake sediment |
October–November |
Participants |
Send sediment sample
bottles to central lab |
December Januari |
Participants |
Send water sampler sheets
to central lab |
December Januari |
Participants |
Analyses of samplers at central lab |
Mid-January February |
RIKZ |
Complete analyses at local labs |
Mid-January February |
Participants |
Send data to central lab |
Early-February |
Participants |
Collate data |
End of February |
Foppe Smedes |
Review data |
At WGs next year |
All |